How Do You Calculate Formwork Quantity?

Advertisements
  • Area of Square = Side x Side.
  • How do you calculate formwork quantity?

    For simple square and rectangular forms, simply multiply length x width to know how much formwork you need. For a circular base, multiply the square of the radius by pi (πr²).

    How do you calculate Batten quantity?

    Multiply the number of rows on each section by the length of the eave of that section. This gives you the total length of battens needed for each section.

    How do you find the shuttering quantity of a beam?

    So, for doing building work, 3 square meter shuttering will be required. For square column, area of the all the sides will be same. So, in this case, the calculation will be done for only one side i.e 0.2 x 3 x 4.

    How do you find the shuttering of a column?

    03. Checking of Column Shuttering

    1. Check the size of shuttering for column and it should be as per drawing.
    2. Check center lines of columns with respect to adjacent columns or as specified in drawing.

    How do I check my shuttering level?

    First check the quality of shuttering plates.



    It should not be bent.

    1. Joints of beam bottom should be properly propped so that formwork doesn’t bulge during concreting.
    2. Before providing beam sides, level of the beam bottom should be checked.
    3. After levelling of beam bottom bracing should be provided.

    What is column shuttering?

    Column box or shuttering for columns is made of plywood sheets or steel sheets fabricated with adequate stiffeners. A thin films of oil or grease should be applied to inner surface of the shuttering to enable easy removal of the column after the concrete hardens.

    How is beam formwork calculated?

    1. Take the cross-section of beam and measure the lengths of the two sides and base of beam.
    2. Sum the three measurements.
    3. Measure the span of the beam.
    4. Multiply the span length by sum of the three measurements (beam base two vertical sides) gives the shuttering area of beam.

    How do you take quantity of steel?

    This can be done by multiplying cross section area of steel by its total length by density of steel which 7850 kg/m3. Total steel quantity of column equal to the sum of both main and stirrup steels.

    How does RCC calculate work?

    For RCC Column, the reinforcement required is 2.5% of concrete volume. Find out the weight of steel with the following formula: =196.25 kg.



    d) Computation of Reinforced Steel:

    1. For slabs = 1.0 % of concrete volume.
    2. For Beam = 2 % concrete volume.
    3. For column = 2.5 % of concrete volume.
    4. For RCC Roads, 0.6% concrete volume.

    What is thumb rule in construction?

    Thumb rule is an approximate & comparing method. … In thumb rules, The units are not the same when we compare to get the results. So never consider units while performing thumb rule.

    What is shuttering material?

    Shuttering material may be made from plywood. The process of shuttering involves setting up temporary structures that will act as molds for concrete as it sets. Shuttering material may include panels, precast molds, and various fastening and support devices known as falsework.

    How do you calculate shuttering quantity for a footing?

    A. Square Footing:

    Advertisements
    1. Volume of concrete = Area of sq. footing x Depth of sq footing. Area of sq. footing = L x B = 0.5 x 0.5 = 0.25 m² Volume of concrete = 0.25 x 0.25 = 0.0625 m³.
    2. Shuttering area = 2 (L + B) x D. = 2 (0.5+0.5) x 0.25. = 0.5m²
    3. Bitumen paint area = Shuttering area + (Top area of footing – column area)

    What is beam formwork?

    Forms are molds to receive concrete in its’ plastic form. Formwork is temporary structure, as such, it is not normally shown on the drawings.

    What is a formwork in construction?

    Formwork is the term given to either temporary or permanent molds into which concrete or similar materials are poured. In the context of concrete construction, the falsework supports the shuttering moulds.

    How do you calculate area of steel?

    Measure the length and width, in inches, of the rectangular steel sheet. For example, the length might be 135 inches while the width is 50 inches. Multiply the length by the width to obtain the area of the steel in square inches.

    What is unit of steel?

    Unit mass of steel is the ratio of weight of Steel to its per unit volume. Usually it is expressed in kilograms per cubic metre or Pounds per cubic feet. Unit mass of steel is 7850 kg/m3 (kilograms per cubic metre) or 490 lbs/ft3 (pounds per cubic feet).

    How do you calculate steel per square meter?

    Thumb rule for Steel required for RCC slab is 80 kgs/m3, then quantity of steel required for 100 sq ft ( 1.416 m3) rcc slab is equal to = 80 × 1.416 = 113.3 Kgs.

    Is formwork and shuttering the same?

    Formwork is a temporary structure which is used as a mould to pour the concrete. Formwork may be the horizontal or vertical arrangement, made to keep concrete in position until it gains desired strength and shape. Shuttering is a part of formwork. … Formwork for columns, retaining walls, footings are known as shuttering.

    How do you calculate shuttering plate weight?

    The formula for weight calculation is:

    1. l = length in mm.
    2. w = width in mm.
    3. t = thickness in mm.
    4. η = Specific material density ( e.g.: steel = 7.85 kg / dm³)

    What is slab formwork?

    It is a permanent or temporary structure in which constructors pour fresh concrete to harden subsequently. … A slab formwork comes in handy when a building requires suspended concrete slabs with no direct connection to the ground. It consists of formwork panels, shores, joists, stringers, and other supporting material.

    What are 2 types of formwork?

    Different formwork types as follows,

    • Timber Formwork.
    • Steel Formwork.
    • Aluminum Formwork.
    • Plywood Formwork.
    • Fabric Formwork.
    • Plastic Formwork.

    What is RCC shuttering?

    Formwork (shuttering) is a temporary mould to provide support to fresh concrete when placed in structural member until the concrete has set. This helps the structural member to gain sufficient strength to carry its self-load and load from other members. … Floor Forms – Formwork for construction of RCC Slabs.

    How do I fill a column in RCC?

    Pouring Concrete,

    1. Column Layout Work: This is the first step of column construction. …
    2. Column Reinforcement Work: When marking of column location is done, the reinforcement of columns are placed according to the structural drawing. …
    3. Column Formwork: …
    4. Pouring Concrete Into Column:

    Advertisements